Procurement #37041



Title
RFB - BP #5 for new Tahlequah Casino - CM CLARIFICATION #10
Status
Active
OpenDate
05/15/2018
CloseDate
05/25/2018
Description
Cherokee Nation Entertainment (“Owner”) on behalf of Foreman Manhattan Construction Team (herein called “Construction Manager”, “CM”, “Foreman Manhattan Team”, “FMC”, or “Foreman Manhattan”) acting as Construction Manager is accepting SEALED bids on Friday May 25, 2018, at 2:00PM CST. The following
Detail
**CM CLARIFICATION #10, DATED 5/25/18, REVISES THE BID FORM AND BID DUE DATE FOR THE INTERIOR AND EXTERIOR STOREFRONT GLASS AND GLAZING ONLY; NEW BID DUE DATE FOR THIS SCOPE IS 6/7/18 AT 2:00PM. SEE ATTACHED CLARIFICATION ATTACHED** **CM CLARIFICATION #9, DATED 5/23/18, REVISES CM BID BOOK AS SHOWN IN THE ATTACHED DOCUMENTS** **ADDENDA #10, DATED 5/22/18, CONSISTS OF 140 PAGES AND ADDRESSES CHANGES TO FIRE SUPPRESSION SPEC, FACILITY STORM DRAINAGE PIPING, AND CHANGES TO THE OVERALL FLOOR PLAN AND WALL SECTION DETAILS AMONG OTHERS. NO CHANGE TO BID CLOSING DATE IS GIVEN. SEE ATTACHED ADDENDA 10 DOCUMENTS** Instructions to Bidders Receipt and Opening of Proposals: Cherokee Nation Entertainment (“Owner”) on behalf of Foreman Manhattan Construction Team (herein called “Construction Manager”, “CM”, “Foreman Manhattan Team”, “FMC”, or “Foreman Manhattan”) acting as Construction Manager is accepting SEALED bids on Friday May 25, 2018, at 2:00PM CST. The following are the only divisions included in BP #5: 10.01 OPERABLE PARTITIONS, 21.01 FIRE SUPRESSION, 23.01 PLUMBING AND HVAC, and 26.01 ELECTRICAL. All proposals should be sent by express delivery, regular mail or hand delivery to Cherokee Nation Businesses Catoosa Corporate office at the following address: IF BY EXPRESS DELIVER OR REGULAR MAIL Cherokee Nation Businesses, L.L.C. Attn: Tina Jones, Buyer IV 777 W. Cherokee Street Catoosa, Oklahoma 74015 IF BY HAND DELIVERY Cherokee Nation Businesses, L.L.C. Attn: Tina Jones, Buyer IV Corp. Building #3 1102 N. 193rd East Ave. Catoosa, OK 74015 Proposals shall be designated as: CNE Tahlequah Casino – Scope Package # _______________ And properly marked with project name, name of bidder and bid package number. Any Proposal may be withdrawn prior to the scheduled time for the opening of bids or authorized postponement thereof. Email delivery of Proposals shall NOT be accepted Proposal Due Date: Due Date: Friday, May 25, 2018 Time: 2:00 P.M. (CST) 3. Content to be included at Foreman Manhattan Construction Team request: Each bid proposal must be submitted on the prescribed form. All blank spaces for bid prices must be filled in, ink or typewritten. Bidder shall submit proposals using the prescribed forms included herein. a. Complete Scope Package Document b. Completed Affidavits c. Pre-qualification Documents (Section 00 45 00) d. TERO bidders must supply a copy of TERO Certificate, front and back. e. One (1ea) soft/digital copy of all the above (*.pdf format) on a USB Thumb Drive Examination of Site: Contractor shall examine site, make notes of existing conditions, comparing such with the plans and specifications, and be fully satisfied as to conditions of such before submitting his proposal. No allowance shall be subsequently made to the Contractor by reason of any error on his part. Pre-bid date is scheduled for: Location: Proposed Project Site 3307 South Seven Clans Avenue Tahlequah, OK 74464 Date: Thursday, May 17, 2018 Time: 11:00 AM CST All Questions and Interpretations of the Bid documents: Project Contact: Tina Jones, Buyer IV (918) 384-7802 Tina.Jones@cnent.com Deadline cut-off date for all questions concerning this specific Bid is 12:00 (Noon) on Tuesday, May 22, 2018.
Name:Tina Jones
Email:tina.jones@cnent.com
Phone:918-384-7802
Cherokee Nation Entertainment
Documents

Code of Conduct

BP 5 Cover & abbreviations

BP 5 Architectural Drawings

BP 5 Electrical Drawings

BP 5 Fire Alarm Drawings

BP 5 Food Service Drawings

BP 5 Landscape Drawings

BP 5 Low Voltage Drawings

BP 5 Mechanical drawings

BP 5 Plumbing drawings

BP 5 Structural Porte Cochere drawings

BP 5 CM Manual

BP 5 Project Manual

BP 1 Specifications

BP 1 Drawings

BP 2 Specifications

BP 2 Cover & Abbreviations

BP 2 Civil drawings

BP 2 Electrical drawings

BP 2 Food Service drawings

BP 2 Low Voltage Drawings

BP 2 Plumbing drawings

BP 2 Structural Drawings

BP 3 Project Manual

BP 3 Drawings

BP 4 Project Manual

BP 4 Cover & Abbreviations

BP 4 Civil drawings 1

BP 4 Civil drawings 2

BP 4 Civil drawings 3

CM Clarification #1

CM Clarification #2

CM Clarification #3

CM Clarification #4

CM Clarification #5

CM Clarification #6

CM Clarification #7

CM Clarification #8

Addenda 1

Addenda 2

Addenda 3

Addenda 4

Addenda 5 drawings 1

Addenda 5 drawings 2

Addenda 5 drawings 3

Addenda 5 drawings 4

Addenda 5 drawings 5

Addenda 6 Civil Const. details

Addenda 6 Civil pgs C0.01 - C1.45

Addenda 6 Erosion Control & Storm Sewer

Addenda 6 Finished Grading plan

Addenda 7

Addenda 8 Architectural drawings

Addenda 8 Structural drawings

Addenda 9

Addenda 10_Specifications

Addenda 10_Architectural pages

Addenda 10_Electrical drawings

Addenda 10_Low Voltage drawings

Addenda 10_Mechanical drawings

Addenda 10_Plumbing drawings

Addenda 10_Structural drawings

CM Clarification #9_corrected

CM Clarification #10_052518

Awards
Cheyenne MEP (Div. 26.02 only)
Kuruks (Div. 10.01 Operable Partitions only)
OCE Mechanical (Div. 23.01 only)